9. Action on Monthly Facilities Matters: FMS Award of Construction, Construction Services Contracts, and Change Order Recommendation
|
Strategic Plan Compatibility Statement:
|
Goal 3 Effective and Efficient Operations
|
Attachments
|
1. Recommendation 2. MPS CONSTRUCTION CONTRACT - Lee Recreation LLC - Tot Lot Replacement - McNair Academy 3. Construction Services Contract-CG Schmidt - CMaR - Milwaukee Recreation Community Center & Browning Playfield
|
File Attachment:
|
|
Background:
|
Listed below are the contracts recommended for the Board's approval at this meeting: Construction Contract Recommended for Approval: - Lee Recreation, LLC for tot lot replacement at McNair Academy; Code: MTN 00 FLR FM ECTS = $163,824.00 Construction Services Contract Recommended for Approval: - CG Schmidt, Inc. for a Construction Manager at Risk for Milwaukee Recreation Community Center and Browning Playfield; Code: CSV 00 RFI RC ECNC = $52,100,000.00 Report of Change Order: - Property Solutions Contracting Corp for 2024 Green Infrastructure Upgrades at MSL & Morse Middle School; Code: MBM PA G54 SL EMTC = $75,500.00
|
Fiscal Impact Statement:
|
This item authorizes expenditures for: Construction Contract: Total Construction Contracts Requested = $163,824.00 Construction Services Contract: Total Construction Services Contract Requested = $52,100,000.00 Change Order: Total Change Order Requested = $75,500.00
|
Implementation and Assessment Plan
:
|
Upon Board approval, the attached construction contract, construction services contract, and change order shall be executed.
|
Recommendation:
|
The Administration recommends that the Board approve the attached construction contract, construction services contract, and change order.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Sean Kane - Senior Director - Facilities & Maintenance Services
|
|
Signed By:
|
|
Michele Wilborn - Budget Analyst
|
|
Signed By:
|
|
Michael Harris - Chief School Administration Officer, Acting
|
|
Signed By:
|
|
Eduardo Galvan - Interim Superintendent
|
|
|
|
|
|
|
|