Meeting Date:
|
1/30/2025 - 5:30 PM
|
Category:
|
NEW BUSINESS (FOR REFERRAL TO COMMITTEE UNLESS OTHERWISE NOTED)
|
Type:
|
Action
|
Subject:
|
11. Action On Monthly Facilities Matters: FMS Award of Professional Services Contracts, Material Purchase, Change Order and Contract Modification Recommendation
|
Strategic Plan Compatibility Statement:
|
Goal 3 Effective and Efficient Operations
|
Attachments
|
1. Recommendation
2. Professional Services Contract - Straightline Moving Inc. - Move Management Consultant Services - Design & Construction
3. Professional Services Contract - Associated Technical Services, Inc. - Contract Labor
4. Professional Services Contract - Service Painting Corporation - Contract Labor
5. Professional Services Contract - Doral Corporation - Contract Labor
6. Professional Services Contract - Quality Electric Service - Electric Motor & Pump Servicing - Facilities and Maintenance
7. Perkins Eastman A1004356 - Contract Extension 2025
|
File Attachment:
|
|
Background:
|
Listed below are the contracts, material purchase, change order, and contract modification recommended for the Board's approval at this meeting:
Professional Services Contracts Recommended for Approval:
- Straightline Moving Inc. for Move Management Consultant Services for Design and Construction; Code: Various = $450,000.00
- Associated Technical Services, Inc. for Contract Labor; Code: Various = See Attachment A
- Service Painting Corporation for Contract Labor; Code: Various = See Attachment A
- Doral Corporation for Contract Labor; Code: Various = See Attachment A
- Quality Electric Service, Inc. for Electric Motor and Pumping Servicing at various MPS locations; Code: Various = Not to exceed $350,000.00 annually
Material Purchase Recommended for Approval:
- Anixter Inc. for Keys and Cylinders at Vincent High School; Code: MBM 0A BDH VN EOSV FEDM= $66,287.82
Change Order Recommended for Approval:
- Poblocki Paving Corporation for the Emigh Playfield and Fieldhouse Renovation; Code: STS 00 RFI C4 ECNC = $159,072.00
Contract Modification Recommended for Approval:
- Perkins Eastman Architects - The Administration is requesting approval to modify the contract from a 10-month contract to a 22-month contract. The vendor was chosen pursuant to RFP #8949, with a term of March 22, 2024 – January 30, 2025. This modified contract will run from March 22, 2024 – January 30, 2026; Code: FAR 00 RDC DW ECNC = $390,250.00 per year
|
Fiscal Impact Statement:
|
This item authorizes expenditures for:
Professional Services Contracts:
Total Professional Services Contracts Requested = Not to exceed $2,150,000.00
Material Purchase:
Total Material Purchase Requested = $66,287.82
Contract Modification:
Total Contract Modification Requested = $390,250.00 per year
|
Implementation and Assessment Plan
:
|
Upon Board approval, the attached professional services contracts, material purchase, change order, and contract modification will be executed.
|
Recommendation:
|
The Administration recommends that the Board approve the attached professional services contracts, material purchase, change order, and contract modification.
|
Approvals:
|
Recommended By:
|
Signed By:
|
|
Sean Kane - Senior Director - Facilities & Maintenance Services
|
|
Signed By:
|
|
Nick Sinram - Director II, Financial Planning and Budget
|
|
Signed By:
|
|
Michael Harris - Interim Chief School Administration
|
|
Signed By:
|
|
Eduardo Galvan - Interim Superintendent
|
|
|
|
|
|
|
|