8. Action On Monthly Facilities Matters: FMS Award Of Construction Contract and Professional Services Contracts; Report With Possible Action Regarding Air Quality
|
Strategic Plan Compatibility Statement:
|
Goal 3 Effective and Efficient Operations
|
Attachments
|
1. Recommendation 2. Contract – ALLCON LLC – Riverside 3. Professional Services Contract – Henneman Engineering Inc. – Golda Meir Upper Years 4. Professional Services Contract – The Concord Consulting Group of Illinois, Inc. – Various 5. Air Quality Backup Contract Information
|
File Attachment:
|
|
Background:
|
Listed below are the contracts recommended for the Board’s approval at this meeting: Construction Contract Requested for Approval: - ALLCON LLC for stage and auditorium lighting at Riverside University High School; Code: SCS 00 UTL DW ECTS = $318,068.00 Professional Services Contracts Requested for Approval: - Henneman Engineering Inc. for new chilled water plant at Golda Meir Upper Years; Code: SCS 00 UTL ME ECTS = $90,000.00 - The Concord Consulting Group of Illinois, Inc., for ESSER II relief fund projects at various MPS sites; Code: Various = Not to exceed 3,000,000.00
|
Fiscal Impact Statement:
|
The item authorizes expenditures for: Construction Contract: Total Construction Contract Requested = $318,068.00 Professional Services Contracts: Total Professional Services Contracts Requested = For a total not to exceed $3,090,000.00
|
Implementation and Assessment Plan
:
|
Upon Board approval, the attached construction contract, professional services contract, and air quality report shall be executed.
|
Recommendation:
|
Your Committee recommends that the Board approve the attached construction contract, professional services contracts, and air quality report.
|